Transporting wind turbine generators weighing 80 tons each posed another challenge: the original port’s cranes had a 60-ton limit. NCL quickly rerouted to Chile’s largest port, San Antonio. However, berths were fully booked, and hurricane season was approaching.

Through urgent coordination, the team secured a 72-hour special operations window from Chilean authorities. All unloading was completed just before weather worsened.
Land transport faced further risks—aging bridges couldn’t bear the weight. The team collaborated with local engineers to install temporary supports. Every meter traveled required precise planning; any misstep could spell disaster.

When the final generator arrived, this battle against time, gravity, and nature ended in victory. More than a transport success, it stands as an epic triumph of modern logistical mastery.